Large logistics base for Luxembourg railways.
The 30,000m² roof with its 254 smoke extraction domes was completed in record time; the installation of the steel deck began in mid-March and the roofs were achieved at the end of June.
To respect the deadlines set, the site was divided into 4 zones, the roofs were carried out successively and without interruption as follows:
– Phase 1 : installation of steel deck on the secure concrete structure;
– Phase 2 : installation of the insulation and waterproofing membrane Sikaplan 1,5mm.
Materials :
Steel deck 153, insulation PIR 9cm, Sikaplan 1.2