Project description : Tereos

Ethanol Production Plant

A general contractor based in Liège was responsible for the construction of this plant. With limited reach in French areas, it preferred to work with local partners to realise these very complex cladding works. The project was a complete success.

 

Material

Double-skin metal cladding on metal frame: 4,500m²
Single-skin cladding on concrete: 4,300m²
Steel deck with polystyrene insulation density 20kg: 3,500 m²