04/08/2017
Some news on our work at the Nanterre site. Our teams did not take holidays during July. The southern part of the roofing is now completed, the Kalzip is being put in place.
Due to the deadlines which have been shortened considerably, we are working simultaneously on the three remaining parts of the roofing (west, east and centre). This change in carrying out the work brings maximum staff into play. Complying with the deadline requested by the customer, principally lies in the supply of product to the work site. In effect, our work requires a supply of more than 450 truck and trailer units. This work of supply and handling products, is even more complicated as the stadium is located in the centre of Paris.
Despite these constraints the customer is most satisfied with our services.